Precast Retaining Wall for RHS Chelsea Flower Show 2024

Gold medal-winning WaterAid garden built on CLF10GS retaining walls

Show Garden Retaining Wall Installation: Project Overview

We were delighted to see our CLF10GS retaining wall units featured in the WaterAid Garden at the RHS Chelsea Flower Show 2024 – a striking, design-led landscape that went on to win a gold medal.

The precast walls provided both structural support and a clean architectural backdrop, forming the boundary on two sides of the garden.

The project had a strict three-week build window, so speed and reliability were essential. Our freestanding walls were installed in just one day using a vehicle-mounted HIAB, giving the landscaping team immediate access to continue work.

Client – Tom Massey Studio

Project – The WaterAid Garden at RHS Chelsea Flower Show 2024

Location – London

Product – CLF10GS

Wall Height – 2.5m & 3m

Wall Length – 32m

Installation Time – 1 day

Installation Team – Landscape Associates + M3

Groundworks – Compacted sub-base and sand blinding layer

Fixing Method – no fixing required

Finish – Hand-rendered by landscape team

Benefits of CLF Walls for Temporary Landscaping Projects

CLF10GS cantilever retaining wall render
Icon for fast installation of precast retaining walls

Fast Installation

32m completed in just one day

Icon for product benefits

No in-situ work

Garden build could begin straight after wall installation

Freestanding System

Walls are easy to remove and reuse post-show

Icon for interlocking concrete wall joints

Perfect Alignment

Tongue and groove joints ensure clean lines for render

Icon showing health and safety for precast retaining wall construction

No Fixings Required

Safer, faster, and cleaner installation

Installation Timeline: In and Out in Record Time

With only three weeks to complete the entire garden, the wall system had to be installed quickly and work the first time. Units were installed using a vehicle-mounted HIAB onto a compacted sub-base and a sand blinding layer. No in-situ concrete was required, avoiding any delays for curing time. 

Once installed, the tongue and groove joints kept the units in alignment – vital for the render finish applied to the walls. The walls supported earth mounds and boulders placed in front and on top, with no movement throughout the show.

Precast retaining walls being installed at the Chelsea Flower Show

Why the CLF10GS Was the Perfect Solution

The CLF10GS retaining wall system offered the speed, simplicity, and structural strength needed for a high-pressure event like Chelsea. As the first component installed on site, the walls provided a solid framework for building the garden around, enabling the team to begin shaping earth mounds, placing boulders, and installing key features.

Using tongue-and-groove joints for alignment and a no-fix installation method, the walls slotted effortlessly into place without the need for drilling, grouting, or delays. Their smooth vertical faces were then hand-rendered, creating a beautiful natural texture that complemented the planting and design.