Precast Silage Clamp for Alderston Dairies
AGRI L & U walls installed in East Lothian to create a high-capacity, SSAFO-compliant clamp.
Silage Clamp Installation for a Jersey Dairy Farm: Project Overview
Alderston Dairies is home to a herd of 300 Jersey cattle in the East Lothian countryside, needed a new silage clamp to replace their Ag Bag system.
Working with our installation partner M3, we supplied and installed a 3m high AGRI retaining wall system designed for long-term durability and high storage capacity.
The clamp was completed in just three days, providing the farm with a more efficient, safer, and Environment Agency-compliant silage storage solution.
Client – Alderston Dairies
Project – Dairy Farm Silage Clamp Construction
Location – East Lothian, Scotland
Products – AGRI-L & AGRI-U
Wall Height – 3m
Wall Length – 133m (total)
Installation Time – 3 days
Installation Team – Modular Cubed
Groundworks – Compacted sub-base and sand-cement blinding layer
Fixing Method – no fixing required
Compliance – SSAFO & Environment Agency design standards
Benefits of CBS Precast AGRI Walls for Silage Clamps
Fast Installation
133m of walling completed in 3 days
High Surcharge Capacity
15 kN/m² for safe silage compaction
SSAFO & EA compliant
Sealed joints for environmental protection
Large-format units
Fewer joints for faster build and better performance
Safe access
Integrated stair sections between bays
Installation Timeline: From Delivery to Storage in 3 Days
Using 2.5m and 5m long precast units, M3 installed the clamp structure in just three days. The freestanding units were placed on a compacted sand–cement footing, with joints sealed to ensure SSAFO compliance.
The new clamp offers improved silage quality, easier handling, and safer working access compared to the previous storage method, giving Alderston Dairies a quality and future-ready silage solution.
Why AGRI Walls Were the Ideal Solution
Silage clamps bear heavy surcharge loads during compaction, along with environmental regulations for safe containment. Our AGRI L and U wall units are specifically designed for these needs, offering a 15 kN/m² surcharge capacity combined with a sealed joint system to prevent effluent leakage.
The U walls serve as an efficient dividing structure between clamp bays, while integrated stair sections create a safe working platform for farm staff. Using large-format units decreases the number of joints that need sealing, speeding up installation and improving durability.